Construction Plans for July 18 - July 25, 2008

WHEN:

7 p.m. to 5:30 a.m. (Night Shift)
9 a.m. to 3 p.m. (Day Shift)

These closures are subject to change; electronic message boards at the work site will display the most recent information as changes occur. 

Along & Near I-25 

  • Waldo Canyon Road will be closed for various bridge operations over the next several weeks. 

  • The La Cienega Overpass is closed for the next several months. The on/off ramps will remain open during this time. Motorists will use the west frontage road to NM 599 for access onto I-25; detour signage will be posted.

  • The East Frontage Road from Waldo Canyon to La Cienega is closed for the next several months.

  • I-25 northbound and southbound at La Cienega will close intermittently from 9 p.m. to 5 a.m.; traffic will be detoured through the on/off ramps.

  • One lane northbound and southbound will remain open at N.M. 14 under the I-25 bridge and at Straight Street in Santa Fe County

  • Right shoulders in both directions remain closed at Richards Avenue and N.M. 599. Flagmen are on site to guide motorists between 7 a.m. to 5 p.m. as needed. Flagmen are also guiding motorists through various parts of Waldo Canyon Road during day and night shifts.

  • Day shift and night shift work will consist of various left lane drops on I-25 between the La Bajada Rest Area and St. Francis Dr. and also on NM 599 at I-25 for various construction operations; motorists should obey posted speed limits and drive with caution. 

** Beginning July 31, crews will begin preparing for a traffic switch on Northbound I-25 near the La Bajada Rest Area. More information will be published as it becomes available.

In the City of Santa Fe

Detours and Traffic Information for construction on Phase II of the New Mexico Rail Runner Express. Work will take place on the Santa Fe Southern line from Rabbit Road to the Railyard.

  • Cordova Road will continue with a full closure through Saturday evening (July 19) for reconstruction. Access to businesses will be maintained, however motorists should detour to Alta Vista Street for access to the NMDOT and Montoya buildings.
    Cordova Detour Map (Map)

  • St. Michaels Drive and Siringo Road will experience a lane drop at night from 7 p.m. to 7 a.m. Tuesday through Friday. One lane will be maintained in each direction.
    St. Michaels Drive (Map)
    Siringo Road (Map)

  • Nighttime lane closures Sunday through Thursday on both Cerrillos Road and St. Francis Drive near the rail road tracks from 7 p.m. to 7 a.m. for the next several months.
    Cerrillos Road/St. Francis Drive (Map)

  • Anticipated daytime lane closures on Zia Road. Construction activity would take place from 9 a.m. to 3 p.m. and between 7 p.m. and 7 a.m. overnight.
    Zia Road (Map)

  • Shoulder closures and possible intermittent lane closures on Cordova and Zia roads throughout the week.
    Cordova Road - (Map)

  • Curb and gutter work is ongoing at Cordova Road between Cerrillos and St. Francis. Those using the sidewalk should use caution or detour to Alta Vista Street.
    Cordova Road (Map)

Plan for Future Construction (Subject to change)

Rodeo Road

Zia Road

Siringo Road

St. Michaels Drive

San Mateo Road/2nd Street

Alta Vista

Cordova Road

Cerrillos Road/St. Francis Drive

 

Rail Runner Phase II

The Details

The construction of Phase II of the New Mexico Rail Runner Express from Bernalillo to Santa Fe is underway and is expected to be complete by December 2008. 

The Extended Route

The train will run on existing BNSF tracks located alongside I-25 from Bernalillo to La Bajada.  Just south of La Bajada new track is being built east of  I-25 near Waldo, to north of the La Bajada Rest Area.  From there it will go through a "tunnel" underneath I-25 to the median between northbound and southbound traffic.  The train will travel in the median, past Richards Avenue then cross under the southbound lanes of I-25 before St. Francis Drive.  From there it will tie into the Santa Fe Southern Railroad.

Rail Runner Route Animation

Rail Runner Rendition SB (wmv 48MB)

Rail Runner Rendition NB (wmv 49MB)

For more information about construction, contact:

1-866-795-RAIL (7245) in the Santa Fe Area

505-245-RAIL (7245) in the Albuquerque Metro Area

Chris Blewett  505-724-3634

 

 
© Copyright 2006 New Mexico Rail Runner All Rights Reserved | Contact | Site Credits